Mineral County Pioneer Council (MCPC) Transit Facility

Architect’s Rendering of Project

trim color changes due to available color options

ARCHITECT:
Slate Architecture
1470 North Roberts Street
Helena, MT 59601
(406) 457-0360

CIVIL ENGINEER:
IMEG
1817 South Ave West
Suite A
Missoula, MT 59801
(406) 721-0142

M.E.P. ENGINEER:
ACE, Inc.
3860 O’Leary Street
Suite B
Missoula, MT 59808
(406) 549-4160

STRUCTURAL ENGINEER:
IMEG
1143 Stoneridge Drive
Suite 2
Bozeman, MT 59718
(406) 600-5331

OUR TEAM OF SUBCONTRACTORS/VENDORS:
4-G Plumbing & Heating
406 Mudworx
Brown Painting
Builders First Source
Counter Solutions
Energy Partners Propane
Epic Steel
Haskins Excavation
Holman Engineers (Testing)
IMEG (Staking)
Jerome Well Drilling
Macon Supply
Marble Creek Construction (Finish Carpentry)
Montana Doorways Plus
Montana Plumbing Company
Northwest Interior Contracting
Pierce Flooring
Pump It Up Pump Service
Quality Seamless Gutters
Riska Insulation
Shadow Paving
Snow Mountain Electric
Wayne Dalton Overhead Doors
Western Drywall
Western Montana Roofing (Roofing & Siding)

STATE BUILDING INSPECTOR:
Shawn Rupp

DRONE FOOTAGE: Jon Schwarder

Status of Project - June 26, 2025: 4G Plumbing and Heating installed insulation as required on duct work; siding install delayed. Western Montana Roofing will now be doing siding installation along with the roofing and will begin Monday, June 30, 2025. We are still on task for completing the siding and roofing install per the May 17, 2025 construction schedule. Our thanks to those on the team who are keeping us on schedule. You are appreciated.

Status of Project - June 17, 2025: Siding material on job site; 4G 90% of rough-in complete but ready for siding install; site visit with owners, architect and engineers completed; inspections completed and ready for siding install; septic drain field installed and currently cordoned off to prevent construction activities from occurring on top.

Status of Project - June 7, 2025: Framing inspection and rough-in electrical in conditioned space inspection completed; Western Drywall installed drywall lid in conditioned space; Western Montana Roofing’s vendor produced roofing material on-site; Montana Plumbing completed rough-in plumbing; 4G in the process of completing rough-in mechanical; siding take-off finalized and Epic Steel has it in production and will be ready next week.

Status of Project - May 30, 2025

Status of Project - May 17, 2025

Status of Project - May 2, 2025

Drone Photos taken by Jon Schwarder April 27, 2025

Status of Project - April 26, 2025 - Framing, Trusses, Septic, Drain Field, Culvert Pipe

Status of Project Continued - April 20, 2025 - Photos of project throughout the week.

Status of Project - April 20, 2025 - Septic tank in place; sewer line from septic to building, two water hydrants, six catch basins, waterline and electrical conduit from well to building, conduit from building to septic for pump and alarm system installed. Framing began.

Drone Photos Taken April 13, 2025 - Photos courtesy of Jon Schwarder

Status of Project - April 12, 2025 Continued - Curbs Poured - Ready for backfill and framing

Status of Project - April 12, 2025 Continued - Foundation Poured

Status of Project - April 12, 2025 - Foundation Poured

Status of Project - April 5, 2025 - Foundation ready to pour April 7, 2025 at 7:30 am.

Status of Project - March 30, 2025 - Foundation prep in progress. Spread footings ready to pour 3/31/25 at noon.

Status of Project - December 27, 2024 - Well drilling complete

Status of Project - November 14, 2024

Status of Project - October 30, 2024

Drone footage taken October 28, 2024 - by Jon Schwarder

Status of Project - October 25, 2024

Status of Project - October 22, 2024

September 24, 2024 - Pre Construction Photos

Status of Project - October 17, 2024 - Mobilization and Pole for Temporary Power

Status of Project - October 18, 2024 - Tree Removal and Site Prep