DiCenzo - Phase II - 2020

Steve and Shelly - Happy Clients!!

Status of Project - August 17, 2020 - Floors are sealed. PROJECT IS COMPLETE!!!

Status of Project - August 14, 2020 - Plumbing is completed. Floors to be sealed 8/17/20

Status of Project - July 22, 2020

Status of Project - July 17, 2020

Status of Project - July 10, 2020

Status of Project - July 3, 2020

Status of Project - June 29, 2020

Status of Project - June 18, 2020 - Metal install complete - working on drywall

Status of Project - June 12, 2020 - Insulation to go in June 15. Rough-in mechanical, plumbing and electrical completed. Metal continues…

Status of Project - May 21, 2020 - Waiting on Metal

Status of Project - May 15, 2020

Status of Project - April 23, 2019 - Concrete Complete and Curing Awaiting Framing

Status of Project - April 17, 2020 - Ground Prep and Underground Plumbing

Status of Project - April 9, 2020 (Includes before and after photos of road)

April 1, 2020 (no joke) - Checking site conditions. Project to begin in the next few days.